911 new doors -On-site visit with EN-HE
→
Europe/Zurich
Meeting 23/04/2025 on-site:
-
Works were planned to start 22nd of April but the contractor pointed out some works to be performed before the intervention.
-
The ladder on top of the existing door needs to be modified before changing the end stopper of the crane.
-
The EN-CV fan control needs to be relocated because the switch of the crane will be placed there
-
In summary: works to do and constrains:

-
The power of the crane switch will be relocated by EN-EL
-
[Action Ixone]: Contact Ming to discuss it. EN-EL intervention is planned before EN-HE'S, so EN-EL will need to come after to relocate the power.
-
The time between the relocation and the power connection, the crane will be unavailable.
-
[Action Ixone]: Contact Philippe (the TSO) to discuss the intervention period.
-
Agreed schedule:
-
The intervention for the endstop modification and the relocation of the switch : 1st week of June
-
Hangers removal: 1st week of June
-
Platform modification: SCE will do it at the same time as the door openings ( beginning of July )
-
Red ladder removal: to be check with SCE if they are planning to do it or it will be under EN-HE's responsibility.
There are minutes attached to this event.
Show them.
The agenda of this meeting is empty