1. GPS
1.1. Previous week: 135In for IDS
- Stable since last wednesday. No call over the week end.
- This morning, call from the user because of slight decrease in the yield, but lasers looked ok, and after reoptimization only 5% improvement which was probably fluctuations.
1.2. Current week: still 135In for IDS
- Run until thursday morning
2. HRS
2.1. Previous week: coupling LIST target
- Installation of the LIST electronics in the HRS HV cage went smoothly.
- Coupling of the LIST target went smoothly.
2.2 Current week: Tm setup and LIST target optimization
- LIST performance assesment and Tm preparation
- Tm was found yesterday and lasers were optimized this morning
- Test on the beamgate leakage earlier today: with 1.4nA of K with BG open, there were no K anymore with BG closed.
- In the coming days, we will finish the LIST/PI-LIST setup/optimization.