- Parts are being machined, components are ordered
- Parts delivery slated for september
- Assembly, calibration, ~ 1.5 months -> tentative delivery date in November ' 25; collector plates probably Q1 2026
- Calibration setup to be reused from HIE-ISOLDE DBsÂ
- Racks already installed on mezzannine, TDC is installed, FESA class still needs to be adapted
- MagneToF high-gain and low-gain modes needed new developements, ongoing, will be integrated in already available PAM infrastructure
- FESA class requirements discussed with users, is feasible with provided hardware