Present: M. Fraser, A. Harrison, J. Samoza, D. Schoerling, P. Schwarz, T. Zickler

Background reading:

Old feasibility study: https://edms.cern.ch/document/3199897/1

Vacuum sectors: https://edms.cern.ch/document/2603395/1

In the event of an MSSB vacuum failure, the present strategy to install windows to isolate the leaking MSSB will impact beam loss in P42 and possibly limit operation of BDF/SHiP operation from 2031.

We have time to prepare a new strategy before 2031.

Discussion:

 

Actions: