I would like to organise a meeting to discuss the installation dates of the ventilation unit and cooling skid
- For the ventilation unit and duct system, we would need to know: the date when we can enter B. 738 and the adjoining galleries. We need to place mobile scaffolding inside the buildings to be able to install the system
- For the cooling skid, it's necessary for the shielding to be ready, as we are placing the skid directly on its top.