• Issues with the CTTx PCB
    • one capacitor for the PS touches the metal enclosure, grounded, causing a short
    • the PCB have been modified and a new production starting (~10k CHF)
    • the estimated delay might bring the CTRx production end beyond Antonio's contract, which for ESE is not a problem to cover if it is just for the mass production 
  • The QSFP proposed by Antonio were not purchased, and therefore are not yet tested: this will be done for the next meeting (July 18th)
  • the ROSA production quantity increase has been agreed with the company
    • from 3000 to 4000 for the production
    • from 50 to 100 for the prototypes
    • the contract might need to be reviewed, but to speed up the process a first order could be placed with the already approved quantitiesÂ