Present: Federico Roncarolo ; Giulia Bellodi <; Jean-Baptiste Lallement ; Edgar Sargsyan , Richard Scrivens

 

We will now operate RFQ2 test bench (with RFQ ready in Aug-Sep 2025). All is ready for this (RFQ BCT and BPM to be installed when RFQ2 moved in final position)

Test bench upgrade document written in 2020 is here:

RFQ_Test_Stand_Future_Proposal_v3_docx_cpdf.pdf

MTP2025 approved full package (basically reallocating budget from RFQ3 production which was canceled)

For BI it is:

Item

Budget

Details

2 x BPMs for ToF

60kCH

"standard" L4 BPM with "standard" DAQ for ToF (present BPM used only via scope for phase meas)

3MeV EM consolidation

30k

Assessment planned for autumn when RFQ test bench starts running

BI-SW grad

90k

Could partially fund new/existing Origin to ensure test bench compatibility with White Rabbit

BI maintenance

25k

For exploitation

Total budget: 205kCH, in principle available from now

Discussion summary: