- Cu-67 development
- About 3-4 MBq collected @01.09.25
- Intervention in S-2 due to MONTRAC shuttle issues.
- The shuttle got stuck in S-6 by the doors to S-2
- The contact power ring was out of the wheel axis and not touching the power rail
- Bug FGC_93 -> update requested at MEDICIS for electrostatic deflector (J. Parra-Lopez)
- Yb-175 ampoule receiving on Wednesday the 3rd
- Decontamination and transfer on 3rd-today
- Tb-149 development run wednesday-thursday morning
- Irradiation 2-3rd September
- Target failed due to ion source cathode-anode contact
This Week
- Yb-175 collection
- Shipping rescheduled to 16th september
- Tb-155 development run from 9th september
- Irradiation of #899M from 3-4th and on 8-9th September.
- Possible ThO2 target material reception from SCK-CEN on friday 9th september
Next week
-
- Tb-155 development run from 15th september
- Irradiation of #899M 3-4th and 8-9th september
- (Optional) Stable beam test of another TaC target with C excess in the pellet mix