WP1: project management (Kati)
- WP2: Coordination of dismantling, installation and services (Laura)
- WP3: ISCOOL Cage Replacement (Lukas)
- WP4: Lasers (KatI)
- Project safety (to be confirmed)
- Challenges and risks: strong interdependence between the different work packages; accessibility and handling in tight spaces, ISOLDE LS3 short duration with a hard deadline in Early 2028 -> Delays will have major impact on the 2028 operation capabilitites
- Budget granted ~ 1MCHF
- Next steps: finalize budget estimation, and circulate Project Management Plan as soon as possible, freeze design to get market survey, planning and coordination