Framework external contractor tasked with the activity, first drawings for proofing produced
- First floor floor composite slab with concrete thickness of 20cm
- Ceiling will be: metal profile sheets that allow significant loads but can be disassembled in the future 
- Total cost estimated around ~300 kHCF, construction about 4 months, start construction works in July 2026 
- Turbo pump evacuation of GPS separator route through the area as they are fed into primary pumps located in the HRS separator zone -> should be reworked to remove radiation load in the area