Proximity of GLM right underneath the laser lab -> possible additional radiation risk to operators in RILIS
- Also potential blocking of both GLM area would create handling constraints of equipment
- Handling on the roof and blockage of the crane: carefully to be reviewed in terms of where the crane can pass and what equipment needs to be craned in place and how (needs individual review of each piece)
- Move transformer of ISCOOL cage to the other side to have easier crane access
- Move Cage access rack closer to cage (on top of cabin) and move chillers downstairs instead