New Hardware is partially included in the approved CONS budget
- New staff and existing GRAF and GRAP will perform the works in this work package
- Removal and decommissioning of the laser system starting end of 2025, to be finished by mid-March 2026
- Storage locations: LARIS lab, YOL2 laser lab and sous-sol, MELISSA, 508 control room and user laser labs; laser tables to be followed up
- Use EAM for tracking of parts 
- Procurement: new laser tables, new lasers, new machine protection system, laser table enclosures and laminar flow units (tasked to the new STAF)
- Installation and commissioning: goal is to have RILIS at same capabilities in 2028 as when stopped in 2025, then continue to expand capabilities throughout the next physics run -> Requires new and trained personal latest in 2027 to be able to operate in 2028