Major activities from technical teams
- New EPC platform, installation starting in February 2026
- Cryomodule 1 removal and refurbishment, March and April 2026 removal, October 2027 reinstallation
- REXTRAP and REXEBIS tests
- Major experiment activities
- ISOLTRAP platform replacement between April and June 2026
- PUMA RC7 installation start in Q1 2026, PUMA tests later 2026
- New COLLAPS and CRIS platforms, tentatively sometime between 2026 and 2027
- Unconfirmed: redesign of GLM/GHM layout
- Experiment testing with local ion sources or radioactive sources at various different experiments