General news:
TestBeam:
- PS between Oct 15 and Oct 29
- 4 GEMs with X&Y view are under test at the GDD: their characterization is on-going with APVs; some time lost in finding the best grounding configuration and a proper HV range to avoid APVs saturation; plans to finish by this month. @Alessandro, any other update on this?
- rotameters: Michele B. has already asked Roberto Guida for 2 pair of rotameter
- scintillators: next week Lisa will be at cern for the characterization of the 3 scintillators we will use in our structure
- structure preparation:
- crane operators have preferred to anchor the structure from the top bosh profiles, while the design was made in view of anchoring the structure from the bottom -> decided to add few extra metallic plate to strengthen the structure; a Bari technician will come next week to cern
- services preparation will be done next week
- DAQ:
- will we use vmm? if so, how many we have?
- if we will go on with APVs, we will not have to many: 11 master and 12 slave
- Monitoring:
- asked for a central grafana and influx -> good for having our setup ready and running also after the testbeam at the north area
- preparation area:
- try to move the structure earlier to PS area to start HV training and gas flushing; in contact with Michael Lazzaroni and Aboubakr Rahmoun
- can you please upload the first tab of the spreadsheet https://docs.google.com/spreadsheets/d/1w229H1DXgvVOeuJRb2cBzjLS8fqi9ZdPFXQQXKAi2uk/edit?usp=sharing with your available days at cern?