Participants: D. Bozzini, D. Ramrekha, G. Georgiev, M. Pérez Ornedo, J. Batista Lopes, N. Dos Santos
P1 - conventional de-cabling waste
1. Duration: 2 weeks, approx. 4 containers/day (with some daily variation). Considered feasible from EN-HE perspective. Containers are CERN property.
· LSSR1 is 11/11/2026 to 25/11/2026 (from EN-ACE planning)
· LSSL1 is 04/12/2026 to 18/12/2026 (from EN-ACE planning)
2. Total: 5x 4m3 skips per side, 10 in total (so 20m3 + 20m3). GMG confirms its initial request.
3. Underground logistics: 4 containers underground at the same time (2 in use, 2 being transported up/down, one per side). EN-HE to confirm availability of trailers for this handling. María
4. Storage underground: Proposal is initially in PM15, then possibly UJ14/16. Co-activity to be checked with Estrella in case trailers/containers need to be moved. GMG to provide a sketch proposing the space to be reserved over the specified period and working methods (two shifts), or use of racks space if already removed. Georgi
5. Once available, DKR/DB to share and validate with Jerome Panigoni. Darshana, Davide
6. No scaffolding required for skip + trailer.
P5 - conventional de-cabling waste
Other EN-EL conventional waste
Space management SharePoints. To share an update with WP15 and space management team. Nuno