- collected data are now available at /eos/project/m/mpgd-hcal/tb25-PS:
- all of us participating should have writing rights
- reading rights guaranteed for all the people in the hcal mailing list
- the drawing with Z-positions info is now available on confluence
position of the third GEM to be updated (-> flipped around Y axis, clock-wise 180˚, plus 90˚ clock-wise around Z-axis)
- 50x50cm2 chambers:
- both MMs are now under reparation at MPT:
- HRS connector with solder on top will be replaced if they didn't manage to clean properly
- all the gas connectors will be replaced
- µRWell:
- first µRWELL ready last friday, while the second one will be ready by this week
- few iteration in the cleaning process because they were drawing current
- 20x20cm2 chambers:
- µRWELL-Fr02:
- Alexis will have a look but he has not yet had the time to look at it
- µRWELL-Fr01:
- DLC connection to ground detached
- Mechanical structure:
- stored at the north area; the lab is not yet equipped with gas lines (not clear when we could start having gas; to be discussed with Karl)
- Electronics box:
- still at PS; open a ticket to understand their issue and it looks tomorrow the transport will happen