Domenico Vicinanza
May, 2007
Major work for EUMEDGRID; major changes in workplan
----------------------------------------------------------------
- SAM Server maintainance (fixing SSL issues due to the new
CERN certificate structure) for the EUMEDGRID installation in Malta.
- Contribution to MEDIAN proposal
- Testing CMS software on EUMEDGRID infrastructure, both using cms VO
and eumed VO, from EUMED UIs (and eumed RB) and CERN UIs (and CERN RB).
Results, organized in a report (HTML and PDF) were distributed within
the WP3 and WP4 EUMEDGRID mailing list
(HTML available here: http://cern.ch/vicinanz/cmstesting/)
- Preparing CMSSW installation scripts to be tested and then
executed as Software Manager on the WNs of the infrastructure to install CMSSW on 14 sites.
- Working on the revised version of the Deliverable 2.2. EU asked CERN
(as responsible for the related Action 2.2) to resubmit it with
updated results and with some more details about interaction
among WP2 and the Infrastructure and Application WPs (WP3 and WP4)
Major work for <GD-OPS; GD-ITR>; major changes in workplan
----------------------------------------------------------------
- SAM Test integration:
ALICE Experiment VOBOX test integration follow up: taking care of feeding MONALISA
with results coming from the VOBOX tests stored in the SAM Production database.
It will be used the programmatic interface and the Grid Monitoring Exchange format.
ALICE people will use those data to trigger their alarms
- SAM Documentation:
-- Completed a developer manual about adding new tests to an existing sensors
(covering existing use cases) and added to the SAM documentation website
(http://sam-docs.web.cern.ch/sam-docs/).
In particular a description about ALICE-VOBOX-like tests use case was added
-- Working on an automatic system to integrate SAM tests source code
documentation into the official SAM documentation repository and website.
Major events attended (include links to event/presentation)
---------------------
SAM Team and IT-GD-OPS weekly meetings
Plans to attend/organize major events (intra-EGEE and others)
------------------------------------------------------------
HPDC Meeting in Monterey Bay in June
Holidays during the period
------------------------------------------------------------
4 day
TimeSheet for the month
------------------------------------------------------------
WP3/A3.2 and 3.3 55%
WP4/A4.2 and 4.3 45%
Infrastructure status
------------------------------------------------------------
# of sites in project: 14 (10 Countries, 8 Mediterranean Countries)
# of sites contributing to the EGEE production infrastructure: 8
# of CPUs: 650
total SE: 7
total CE: 10
total gCE: 2
total RB: 5
total gRB: 2
total FTS: 0
total LFC: 1