Bumper
FS, DR are ready
ES tbd q1/2026
budget 200 kCHF
3D technical drawings are done, the work on 2D ones are ongoing

Wobbler
ES tbd q2/2026
budget 15 kCHF -> (50 kCHF with plug-in supports)
It is enough time to make a new design for the plug-in supports

Dilution magnets
FS, ES are not ready yet
Budget 65 kCHF
Waiting for input from STI to decide on the number of magnets. (coming in ~2 months) (Action: STI and WP2)
- Deadline for the ES? - No 

DS budget code includes "production of the laminated MDX". We need to double-check that.

P42 beamline reconfiguration
ECR tbd
New cables, water hoses, etc. Same number of PCs up to DS, Same number of MDXs  
Needs to be finally defined to have some time for the cabling request. (Action: Laurie and Fabian)
Budget? -Estimation is ongoing 
Order of magnitude -300 kCHF

Laminated MDX
number - 4 (11)
FS, ES tbd
Budget 300 kCHF (for 11)
Waiting for decision if we need it. Looking at the simulations, we don't need it, but the is no final decision.
Decision deadline (?): Production takes 2-2.5 years (second half of 2028)
Decision to be taken before the TDR