- They have four cables around this area -> all being removed now by EP (to follow up with Liss/Hanne this happened)
- two for collaps
- one for vito
- one for cris
- Liss mentioned they have a PhD student who will be rebuilding the gray cage
- It will be skinnier and longer
- This will be done between March - Sept
- Need to coordinate well with Liss for activities of dismantling RILIS and their PhD work
- Are people allowed to work in that area while dismantling is ongoing?
- Also mentioned in one of the integrations there was a post put infront of their small cage which does not work as it blocks their window
- Either the pillar needs to be moved, or a window throughthe pillar needs to be put in place.