• Cables
    • For suspending the cables SCE has said they can easily attach them onto the scaffolding - however, this would mean they would still require suspension for 1 week as the time it takes to detach the cables, then build scaffolding, then attach cables to scaffolding this would be the estimated lead time.
    • A new on-site visit will be requested in order to see if a temporary frame can be built over the beamline in order to rest the cables on that, but there is limited space
      • If possible / space allows, mechanical protection over the beamline is preferabe as this would then protect even from the construction of the scaffolding itself
  • Protection of equipment
    • The idea is this will now be done by RBS. Timeline still TBD.
  • Working footprint attached
    • This shows the area that will be worked on taking into account both the dismantling as well as the construction phases
  • GPS exhaust vac pipes
    • Re-routing not possible
    • plan b - will design a permanent shielded box
  • Dismantling
    • CV
      • require 2 weeks
      • space for 2 pallets for dismantling of AC units and ducts
      • Route for removal of pallets?
    • ACE
      • 3 weeks end of may/ early june
      • green cage and light structure
      • Route to be defined and location of pallets to be defined
  • Integration
    • Meeting tomorrow afternoon for revision of current integration
  • Planning
    • Carlotta to come up with a master plan which integrates all groups on a weekly block schedule
    • This can then be circulated among relevant groups by management
    • ECR for EP cage change?