• Major installation advancements at AD -> Magnet is now cooling down, it is planned to take Antiprotons in March when AD is back and running again
  • ECR for RC7 (PUMA at ISOLDE experimental area) now ready to be shared in engineering check
  • PUMA installation planning at ISOLDE: transport planned with Antiprotons or electrons planned for second half of the year, RC7 will start construction at ISOLDE in Spring to anticipate transport later in the year 
  • Transport still needs production of load spreader -> needs to be announced at least 3 months in advance; needs also preparing the Diesel generators and renting of the special truck 
  • Concerns by VSC: only time for support until July (start of LS3), afterwards will be very tight on ressources 
  • Mark will send Vincent the final RC7 layout to be integrated