- Major installation advancements at AD -> Magnet is now cooling down, it is planned to take Antiprotons in March when AD is back and running again
- ECR for RC7 (PUMA at ISOLDE experimental area) now ready to be shared in engineering check
- PUMA installation planning at ISOLDE: transport planned with Antiprotons or electrons planned for second half of the year, RC7 will start construction at ISOLDE in Spring to anticipate transport later in the year
- Transport still needs production of load spreader -> needs to be announced at least 3 months in advance; needs also preparing the Diesel generators and renting of the special truck
- Concerns by VSC: only time for support until July (start of LS3), afterwards will be very tight on ressources
- Mark will send Vincent the final RC7 layout to be integrated