EPC platform:
Scaffolding for the work on cable trays (and cabling) at the new EPC platfom will be put in place the coming days.

Construction area at LA1 for the prefabrication of the platform cable trays - passage kept free (but pay attention).

Racks for the platform coming towards the end of this week (Rustan) - old ventilation handling work taken in account (Melania)

During the arrival of the racks the 508 side entrance will be blocked for a few hours.

 

MULTIPAC concrete slab next to 508 done last week. Chiller placing foreseen for Monday 09/02 - has not been done yet?

 

Weekly schedule

AOB