- EN-EL to disconnect electrical power supply
- Xavier to follow up with Andy directly
- No news on quotation - means no news on equipment dismantling on roof
- Hopefully start next mon
- Require 2 weeks total. Likely 1 week should be sufficient
- Start with preparation of roof tomorrow
- Xavier to order his own pallets to place equipment
- Pipes below RILIS finished last week