• EN-EL to disconnect electrical power supply
    • Xavier to follow up with Andy directly
  • No news on quotation - means no news on equipment dismantling on roof
    • Hopefully start next mon
    • Require 2 weeks total. Likely 1 week should be sufficient
  • Start with preparation of roof tomorrow
  • Xavier to order his own pallets to place equipment
  • Pipes below RILIS finished last week