• Just waiting on green light for the survey
  • After the survey is done, we need to validate cables to be removed, and then decabling and suspension can proceed
  • Start survey tomorrow (providing contractors have the manpower)
    • Technical visit planned for this afternoon with contractor
    • Either Laura or someone else from the RILIS team to be present during the survey for efficiency and validations
  • Week 11 - decabling and suspension starts