• Equipment
    • Rack to be removed this week
    • Remaining teslameters removed this week by Julien
    • Frame to be built this week by Oscar
      • Dust protective plastic layer to be put up week 11
    • Equipment on hall floor removed by the end of this week
    • sas to be emptied by the end of this week
    • Green cage final inventory tomorrow
  • EN/EL
    • Technical visit yesterday for decabling/suspension capagn with EN/EL
    • Started this morning with a survey of cables, survey continuing through to thurs latest
      • Decabling and suspension planned to start week 11
    • IT VIC complete, cables to be removed tomorrow and thursday
  • Integration
    • HRS door to be replaced completely
    • SCE investigating placement of shielding (earthquake safe) above the SSP areas
    • Tomorrow morning dedicated to on-site checks to confirm new platform design fits with current model
    • To be confirmed with crane support on crane access to SSP area with new roof in place
  • CV
    • Pipes under bunker removed
    • Still waiting on contractor quotation, hopefully start with roof equip removal next week
  • Safety
    • Lead to be removed once roof removed using crane - Jonothan/Olivier to perform Pb dust checks as step1
    • Old source safe and shielded containers in back corner of old control room, to be transferred to SSP and then verified in fumehood
  • Planning
    • Weekly coordination meeting between groups involved every monday at 9am