- Equipment
- Rack to be removed this week
- Remaining teslameters removed this week by Julien
- Frame to be built this week by Oscar
- Dust protective plastic layer to be put up week 11
- Equipment on hall floor removed by the end of this week
- sas to be emptied by the end of this week
- Green cage final inventory tomorrow
- EN/EL
- Technical visit yesterday for decabling/suspension capagn with EN/EL
- Started this morning with a survey of cables, survey continuing through to thurs latest
- Decabling and suspension planned to start week 11
- IT VIC complete, cables to be removed tomorrow and thursday
- Integration
- HRS door to be replaced completely
- SCE investigating placement of shielding (earthquake safe) above the SSP areas
- Tomorrow morning dedicated to on-site checks to confirm new platform design fits with current model
- To be confirmed with crane support on crane access to SSP area with new roof in place
- CV
- Pipes under bunker removed
- Still waiting on contractor quotation, hopefully start with roof equip removal next week
- Safety
- Lead to be removed once roof removed using crane - Jonothan/Olivier to perform Pb dust checks as step1
- Old source safe and shielded containers in back corner of old control room, to be transferred to SSP and then verified in fumehood
- Planning
- Weekly coordination meeting between groups involved every monday at 9am