- STI / HE
- Dust protective plastic layer to be put up starting today
- Displacement of patch panel either this week or next week
- Gas lines in ISCOOL removal this week
- EN/EL and EN/CV dependent will potentially open roof hatch and remove tables and lead during week 13
- EN/EL
- Decabling and suspension started yesterday
- Cables around tape station will be placed around equipment since no frame in this area was built on time (see photo)
- Roof cables suspension week 12
- Small cable trays and cables supporting communication wiring at GHM removed this morning
- Rack next to ISCOOL cage craned out yesterday
- Integration
- HRS door
- Meeting planned tomorrow with Didier for new design
- Replacement timeline still TBC
- Meeting with EN-EL this afternoon to hopefully get more details on their side including integration of cables below RILIS
- CV
- Roof equip. removal started yesterday and ongiong for this week and next week as a buffer
- ACE / HE
- Shifting dismantling of green cage forward, this will now start week 14
- Scaffolding around SSP area will go up the week before in week 13
- Confirmed with Jordi everything will be dismantled including all removed from the ISOLDE sas by the end of week 15 latest
- Safety
- Project safety meeting tomorrow morning
- RP monitor on roof of RILIS to be removed (see photo)
- Planning
- Weekly coordination meeting between groups involved every monday at 9am - Please contact Laura/Kati if you have not had an invite but would like to attend