On behalf of the project:
Past week:
- Continued with excavation of non-radioactive soil evacuation (working in the area between B. 198 and B. 170
- Pre-construction of the niche for the GPS camera finalized.
- Intallation of liner in the storage pit
- Sprinckler system installation (dust management).
- Covering of GPS/HRS radioactive soil areas
- Testings cleaning procedure for excavation machines
- Cleaning of shielding blocks on top of the GPS dump before handling
This Week:
- Core drilling for the camera niche
- Radioactive soil removal to reach the level 440.5 m.
- Cleaning of blocks in dedicated tent (tests)
- Handling of blocks on top of the GPS dump