HRS field control and measurement:
- Request from Marco Buzio TE/MSC to house a full 19" rack. Proposal in x-entrance 170 R-020 with cables trhough existing hole (if fits with Ar/N2 and AC tubes). Would require to move the two spare-parts EPC cupboards elsewhere. Discussed with Vincent Barozier. To be discussed at the ICL.
Separator Areas
- Acces planned tomorrow 18/03 for 3D and equipment removal to prepare future core drilling (new survey lines)
Target Area and BTY line work
- Section of the BTY line vacuum pipe in Front of the GPS Faraday cage will be removed by TE-MSC on Thursday (needed for shielding installation)
- Work preparation ongoing for BTY line disamantling. BHZ magnets don't fit through the current shielding door opening. Need to cut 10 cm of wall in the corner.
- Meeting next week: BTY Power converters consolidation - Work in Building 197. Review ECR and plan the work.