- Outside work for pipe/duct work for EN-CV finalized (insulation in place)
- Until mid-April, SCE-SAM will build the lateral protection wall for the ducts and prepare the area for the final shielding construction (needed for stray radiations) which will be included in the IBDRS phase 2 project.
- Ongoing work inside Build. 197
- Commissioning and reception of the new ventilation system expected Week 17
- 20/03 craning planned for equipment delivery
- Will communicate the date for the re-connection of the turnstile for access (requested to be done during the coming week).