ISOLTRAP:
- Platform replacement preparations: VITO laser tube (high section) and tall pillar removal to be organised (Transport / VITO users?)
- Emergency wall cutting/carrotage: Preparations mezzanine side done: Power outlets moved, ground cable and ethernet rerouted. Order launched with the contractor. BC still needed for material and work-order for the ISOLTRAP platform itself (Severin d'Armancourt). Wall cutting either early April wk14 or 15 (Easter) or end of April/ beginning of May (due to the need of the overhead crane it needs to be outside CM1 handling dates).
ISS:
- He filling done
- Connection to diesel network (James Devine) -> planned for 24 March
SAS and storage status
- Edinburgh chamber has been dismantled and will be sent back -> Alu boxes in shelves + wooden box will be gone
Requests
- Pressured air for testing valves implantation chamber
Weekly schedule:
https://cernbox.cern.ch/s/WPuwNnMp3GkhtvX