• STI
    • Dust protective plastic layer has started being installed - SSP area priority
    • Patch panel has been shifted, a new frame will be built to secure it in place more than just zipties
      • If people like this new more accessible location, we could consider keeping it there in the long term
    • Clean up of roof either this coming Friday or Monday
    • New frame to be built by HRS door to hold cables, this will not obstruct the opening to the separator area
      • HRS door has been removed and the same lock cylinder has been taken from this door and placed in the second door through the chicane - so the key for access remains the same
    • Preparation and removal of lead hopefully next week
  • EN/EL
    • Decabling and suspension has finished below the barrack (minus a few cables through the I-beam which we will hopefully remove when dismantling via some screws)
    • Cable on roof to be shifted from wed-fri this week
    • Antenna on roof is dismantled
  • Integration
    • SCE contribution including new platform design, cross-beam shifted to new position, and re-positioning of primary beam next to BI rack to be updated with 3D model to be done today/tomorrow latest
  • CV
    • Roof equip. removal finished
    • Final pipe removal for inside the lab technical visit today
    • Compressed air line
      • Needs to be replaced by flexible line due to access restrictions
      • Cannot find isolating valve, therefore will need to cut compressed air to the entire hall
      • Timeline  - before end of April
  • SCE / ACE / HE
    • Opening of roof hatch 24.03
    • Tables inside RILIS to be removed next week
    • maybe starting to move some shielding blocks between RILIS and GLM starting next week - TBC
    • Shifting dismantling of green cage forward, this will now start week 14
    • Scaffolding around SSP area will go up the week before in week 13
  • Safety
    • Project safety meeting last week with new light on some requirements towards fire safety of beams
    • RP monitor on roof of RILIS being removed as we speak (helmet on)
    • Fire detection system removed last week
      • The pipe from the fire detection system was cut by another group prior to dismantling - equipment tampering, EN/AA to decide how to proceed
  • Planning
    • Weekly coordination meeting between groups involved every monday at 9am - Please contact Laura/Kati if you have not had an invite but would like to attend