- STI
- Dust protective plastic layer has started being installed - SSP area priority
- Patch panel has been shifted, a new frame will be built to secure it in place more than just zipties
- If people like this new more accessible location, we could consider keeping it there in the long term
- Clean up of roof either this coming Friday or Monday
- New frame to be built by HRS door to hold cables, this will not obstruct the opening to the separator area
- HRS door has been removed and the same lock cylinder has been taken from this door and placed in the second door through the chicane - so the key for access remains the same
- Preparation and removal of lead hopefully next week
- EN/EL
- Decabling and suspension has finished below the barrack (minus a few cables through the I-beam which we will hopefully remove when dismantling via some screws)
- Cable on roof to be shifted from wed-fri this week
- Antenna on roof is dismantled
- Integration
- SCE contribution including new platform design, cross-beam shifted to new position, and re-positioning of primary beam next to BI rack to be updated with 3D model to be done today/tomorrow latest
- CV
- Roof equip. removal finished
- Final pipe removal for inside the lab technical visit today
- Compressed air line
- Needs to be replaced by flexible line due to access restrictions
- Cannot find isolating valve, therefore will need to cut compressed air to the entire hall
- Timeline - before end of April
- SCE / ACE / HE
- Opening of roof hatch 24.03
- Tables inside RILIS to be removed next week
- maybe starting to move some shielding blocks between RILIS and GLM starting next week - TBC
- Shifting dismantling of green cage forward, this will now start week 14
- Scaffolding around SSP area will go up the week before in week 13
- Safety
- Project safety meeting last week with new light on some requirements towards fire safety of beams
- RP monitor on roof of RILIS being removed as we speak (helmet on)
- Fire detection system removed last week
- The pipe from the fire detection system was cut by another group prior to dismantling - equipment tampering, EN/AA to decide how to proceed
- Planning
- Weekly coordination meeting between groups involved every monday at 9am - Please contact Laura/Kati if you have not had an invite but would like to attend