Updates:
- Mechanical completion inside 197/2-401 by end of March
- Commissioning will start 1st April
- Waste removal inside 170/2-402 ongoing
- Turniquet -> awaiting for new gate pillar's modifiction ( end of April)
Piperack area:
- Vertical shielding 20 April - 2 weeks
- HV cables reconnection early May