- STI
- Dust protective plastic layer ongoing - SSP area complete
- Patch panel fixed in position - if no objections, can leave in current position - more accessible!
- EN/EL
- Cable on roof has been shifted
- To design a small standing structure allowing remaining cables resting on roof to be suspended - design ongoing
- Remaining lights and cables to be removed from inside lab thurs/fri this week
- Temporary lights to be put in place to help with remaining works inside lab
- Cable tray above GHM to be removed this thurs/fri
- Integration
- Vincent marked on the floor around ISOLDE the Beam positions - these are now finalised in the integrations
- CV
- Pipe inside lab
- Require access to separator area in order to see where this pipe leads
- Compressed air cut meeting planned for tomorrow
- SCE / ACE / HE
- Opening of roof hatch
24.03 DELAYED
- Problems with acess to hatches with PUMA attachment on crane
- Scaffolding around SSP area will go up tomorrow
- Dismantling of green cage starting on Monday
- Removal of racks and transformer
- Removal of survey points in GLM/GHM confirmed with BE/GM
- VIC for the removal of the green cage planned for Friday.
- Safety
- Planning
- Weekly coordination meeting between groups involved every monday at 9am - Please contact Laura/Kati if you have not had an invite but would like to attend