• STI
    • Dust protective plastic layer ongoing - SSP area complete
    • Patch panel fixed in position - if no objections, can leave in current position - more accessible!
  • EN/EL
    • Cable on roof has been shifted
      • To design a small standing structure allowing remaining cables resting on roof to be suspended - design ongoing
    • Remaining lights and cables to be removed from inside lab thurs/fri this week
      • Temporary lights to be put in place to help with remaining works inside lab
    • Cable tray above GHM to be removed this thurs/fri
  • Integration
    • Vincent marked on the floor around ISOLDE the Beam positions - these are now finalised in the integrations
  • CV
    • Pipe inside lab
      • Require access to separator area in order to see where this pipe leads
    • Compressed air cut meeting planned for tomorrow
  • SCE / ACE / HE
    • Opening of roof hatch 24.03 DELAYED
      • Problems with acess to hatches with PUMA attachment on crane
    • Scaffolding around SSP area will go up tomorrow
    • Dismantling of green cage starting on Monday
      • Removal of racks and transformer
      • Removal of survey points in GLM/GHM confirmed with BE/GM
      • VIC for the removal of the green cage planned for Friday.
  • Safety
    •  
  • Planning
    • Weekly coordination meeting between groups involved every monday at 9am - Please contact Laura/Kati if you have not had an invite but would like to attend