ISOLTRAP:
- Platform replacement preparations: VITO laser tube (high section) and tall pillar removal to be organised. VITO has been informed (Mark, Magda, Nikolay)
- Emergency wall cutting/carrotage: VIC scheduled for 15/04. Wall cutting/core drilling scheduled for week 18 (27-30 April) (Severin/contractor). Crane needs a lock-out during 3-4 days (after CM1 handling and in line with ISOLTRAP activities but RILIS activities to be checked)
- Preparations mezzanine side done: Ready for CE work apart from cable tray bracket and pipe holders on the ISOLTRAP side.
- This week clash: ISOLTRAP LHe dewar handling on Wedn 25/03 9-11h30 (cannot be postponed: critical level) clashes with crane lock-out for scaffolding installation at GLM/GHM for RILIS project. Work not at height (?).
Solution to be confirmed: Crane remote stays with EN/HE transport(Yann) from Tues 16h - Wedn 16h (during scaffolding installation). Taking Technical Note in account (paragraph 3.5 on ISOLDE) GESTION DES COACTIVITES Interférences moyens de travail en hauteur / ponts roulants. https://edms.cern.ch/document/3279995/1.0
ISS:
- Connection to diesel network (James Devine) -> today 24 March
Beamlines:
-
- Reminder of compressed air issue at GHM (hissing sound - mail Laura 20/3)
- Can the compressed air be stopped at GHM and kept at GLM
- VITO is preparing move of magnet to 275, timing will be adapted taking into account other hall activities
- VITO move of equipment
- Clarify duration and extend
- ISOLTRAP platform
- Wall cutting emergency windows
- Proposal to meet next week to check general status of the hall and see what needs removal before cryomodule
- PUMA - drilling of holes in the floor