- STI
- Dust protective plastic layer ongoing
- Frame around HRS door to be done this week for cable suspension
- EN/EL
- Remaining lights and cables inside lab, cable tray above GHM, and electrical box on roof removed last week
- CV
- Pipe inside lab removed
- Compressed air line
- Waiting on confirmation of dates
- SCE / ACE / HE
- Dismantling of green cage started yesterday
- Removal of racks and transformer later this week
- Dismantling of green I-beams planned for next week
- AOB (dont have the rights to add minutes to other sections in this meeting)
- VIC with Nenad for fiber optic this morning - works should be complete on top of RILIS, only required 1h and started at ~9h30 this morning
*Planning: Weekly coordination meeting between groups involved every monday at 9am - Please contact Laura/Kati if you have not had an invite but would like to attend