µLoop (Stefania):
- 1/2 day for pipes modification (the new pump model has the inlets on the top instead of the side)
- 2 days for the electrical connections (alim + widgetlord board + dew point + pressure sensor)
- currently missing the alim and pressure sensor
- ideally to be done before May
-frame for RPC detector
-CHARM
(dry run 29/4 - run 6/5)
-NA61 safety valve to be done after April 1st -> Davide