Upcoming experimental activities
Coactivity management
Weekly schedule
https://cernbox.cern.ch/s/WPuwNnMp3GkhtvX
Potential issues:
- Friday 24/4: ISOLTRAP craning and PUMA crane removal
- IDS measurements >< RC6 EN/EL
- Monday 20/4 - Friday 24/4 Parking 170 blocked
- LHe2 delivery for ISOLTRAP 22/4
To note
- Thursday 23/4 or Friday 24/4: Transport CM1 from ISOLDE to SM18
- Wed 15th of April until 14th of May: 1 month road closure Democrite
Summary from meeting 1st of April
Week 17 - Monday 20/4
Week 18 - Monday 27/4 (4 days only)
-
Entire week: drilling of emergency exit of ISOLTRAP platform (noise to be expected)
-
28/4: VITO magnet transport with crane (1h)
-
Exact timing to be coordinated: RILIS cabin roof hatch opening/laser tables (if they physically fit) and lead handling -> crane needed frequently (1-2 days in total?)
-
Start CRIS measurement campaign
Week 19 - Monday 4/5
-
Start EN-ACE works to dismantle RILIS light structure (crane needed occasionally, certain amount of noise to be expected)
-
Continue CRIS measurement campaign
508
- Water leak next to transformers (?) 508
- Long pipes next to 508 - EN/CV
- Technical galleries works - status relaunched