- STI
- New temporary frame around HRS door built and in place
- CV
- Compressed air line below barrack replaced with flexi hose
- valves installed for future modifications made easier
- ACE / HE
- Small laser tables removed and now in storage
- Light structure material sas disassembled
- Week 17, Fri 24th:
- Modification of PUMA attachment
- Scaffolding modifications and additions
- Works on hold for cryomodule transport, week 18 main works to continue
- Integration
- Meeting last week on evacuation path
- no objections to pilar placement below the beamlines
- Meeting last week with users discussing placement if pillars
- OK given for current positions
- RP
- Do we de-classify GLM area or put up barriers as a temporary wall to stop entry from stairs side once shielding blocks removed?
- AOB
- Shielding block storage in SSP area?
- "Fresh" laser dye found on I-beams below barrack around tape station - to be inspected today