• Scaffolding (fri 24th - mon 27th)
    • Modifications to current scaffolding around green I-beams
    • Addition of scaffolding below green I-beams near the tape station
    • Addition of scaffolding on roof of RILIS in order to suspend remaining cables
      • Drilling into wall and shielding in order to errect scaffolding required
  • ACE / HE
    • Next week:
      • Removal of green I-beams

      • Opening hatch on roof

      • Removal of remaining big laser tables

    • Week 19/20
      • Light structure disassembly
  • EN / EL
    • Next week:
      • 1/2 day required (w/ crane lock out) for suspension of cables on roof and removal of cables inside lab now that tables are removed - potentially mon 27th
  • Integration
    • Meeting thurs to discuss shielding blocks
  • RP
    • GLM/GHM now declassified to same as rest of the hall
  • AOB / safety
    • Fri 24th: Modification of PUMA attachment
    • Laser dye
      • fresh dye seen last week, confirmed not fresh and is old dye that was knocked down during cable movement
      • HSE visit planned fri to discuss how to proceed when working with dye contamination
    • Vac pipes
      • Visit planned thursday with potential contractor to see feasibility of handling