Modifications to current scaffolding around green I-beams
Addition of scaffolding below green I-beams near the tape station
Addition of scaffolding on roof of RILIS in order to suspend remaining cables
Drilling into wall and shielding in order to errect scaffolding required
ACE / HE
Next week:
Removal of green I-beams
Opening hatch on roof
Removal of remaining big laser tables
Week 19/20
Light structure disassembly
EN / EL
Next week:
1/2 day required (w/ crane lock out) for suspension of cables on roof and removal of cables inside lab now that tables are removed - potentially mon 27th
Integration
Meeting thurs to discuss shielding blocks
RP
GLM/GHM now declassified to same as rest of the hall
AOB / safety
Fri 24th: Modification of PUMA attachment
Laser dye
fresh dye seen last week, confirmed not fresh and is old dye that was knocked down during cable movement
HSE visit planned fri to discuss how to proceed when working with dye contamination
Vac pipes
Visit planned thursday with potential contractor to see feasibility of handling