LS3C committee tomorow with presentation on CM1 refurbisment and possibly CM5 production

 

(ES)
News on the 833 Technical Gallery work (Florent Legay):

Possibility to keep access to 508 (mandatory for the consolidation and ongoing works) via a ramp.
The ramp construction will take approximately one week. During this period, access to the building will be limited.
Ramp construction could start the work in mid-May, with the exact date to be confirmed following ISOLDE approval.

The ramp will allow vehicles with loads of up to 12 tons per axle, with only minor deformation expected.

(See attached pdf)