- Emergency wall cutting/core drilling scheduled for week 18 (27-30 April) (Severin/contractor). Horizontal core drilling will be done Mon/Tues 27/28 April: Crane still available. Followed by vertical core drilling where crane support and lock-out will be needed on Wedn/Thursd 29/30 April.
All activities have been adapted to fit workable schedule (see machine activities - planning).
- ISOLTRAP side cable tray bracket and pipe holders to be removed (Oscar/Erwin) - to be done.
- ISOLTRAP platform replacement work: 18th June scaffolding - first platform part to finish ~22 July.
- Platform replacement preparations: VITO laser tube (high section) and tall pillar removal to be organised. VITO has been informed (Mark, Magda, Nikolay) -> to be done. Request to have the tube back in place as soon as the scaffolding is in place / fixed to the scaffolding to facilitate VITO to run their laser - to discuss with contractor.
- ISOLTRAP filling / dewar craning in line with the CM1 handling activities in wk 16 / 17 (see machine activities - planning).
WISARD:
- planning to come 15 - 19 June to mount the setup for off line data taking
- week 27 (29 June) to cooldown the magnet
- taking data wk27-29 until July 19
- Coordinate with ISOLTRAP & RILIS work. Crane needed for dewar craning WISARD
Beamlines:
- VITO is preparing move of magnet to 275: foreseen for Tuesday 28 April - Brucker specialist for specific rods inserts and handling. In line with planning.
- VITO move of equipment
- Jura side HIE tunnel had been cleared - many thanks! Material can be moved back: CM1 tunnel roof work has finished.
- ISOLTRAP platform
- Wall cutting emergency exit - next week 18.
- Please maintain the SAS empty until after 23rd April (CM1 transport to SM18).
- PUMA - RC7 installation work on supports and equipment ongoing
- During the cables testing (new EPC power supplies) a french to swiss power adaptor at CRIS was damaged casuing a multi power extension to trip. The adaptor has been replaced and power restarted. Tthe users (Bram) have been asked to verify their equipment (puming units).