ISOLTRAP:
- Emergency wall cutting/core drilling ongoing as planned (Severin/contractor). Horizontal core drilling will be done Mon/Tues 27/28 April: Crane still available. Followed by vertical core drilling where crane support and lock-out will be needed on Wedn/Thursd 29/30 April.
Fits with all other activities
- ISOLTRAP side cable tray bracket and pipe holders were disconnected by the contractor - Thanks!
- ISOLTRAP platform replacement work: 18th June scaffolding - first platform part to finish ~22 July.
- VITO laser tube is to stay in place: Has been discussed with the scaffolding organising responsible (Michael Bourbon). Laser guidance tube to be connected to the scaffolding and vertical pillar to be removed. To be noted on the scaffolding contractor's work order at the next occasion.
- ISOLTRAP filling / dewar craning in line with the CM1 handling activities in wk 17 / 18 (see machine activities - planning).
WISARD:
- planning to come 15 - 19 June to mount the setup for off line data taking
- week 27 (29 June) to cooldown the magnet
- taking data wk27-29 until July 19
- Coordinate with ISOLTRAP & RILIS work. Crane needed for dewar craning WISARD
Beamlines:
- VITO magnet has been lifted out and transported to 275 - Brucker specialist for specific rods inserts and handling
- VITO suggests a marked pathway along the Jura side of the HIE tunnel to avoid blockage with equipment
- ISOLTRAP platform
- Wall cutting emergency exit - ongoing
- PUMA - RC7 installation work on supports and equipment ongoing
- PUMA LS running discussed with Richard Scrivens & Mark Kirschbaum - to secure, as planned, services from the groups from Aug '26 - start 2028.
- CRIS asked for the use of the ISOLTRAP (CDO) end-FC pico amp box to ready out their signals - BI rack and FE are off. Suggestion to use the manual Keithley pico ampere meter(s) standing in the old control room