- Scaffolding (fri 24th -
mon 27th today)
- Modifications to current scaffolding around green I-beams
- Addition of scaffolding below green I-beams near the tape station
- Addition of scaffolding on roof of RILIS in order to suspend remaining cables
- ACE / HE
- Yesterday succesfully opened roof hatch, removed laser tables and shielding blocks from inside the lab (see photo!)
- Starting Thurs:
- Week 19/20
- Light structure disassembly
- EN / EL
- Yesterday finished suspension of cables on roof
- Wed:
- removal of cables inside lab as well as end caps on remaining cables below barrack
- AOB / safety
- Lead
- to be removed from RILIS this week
- RP to perform their controls in b.179
- Laser dye
- Details for handling to be outlined in an IMPACT (to be confirmed with HSE)
- Contaminated pieces to be seaparated for waste
- Will try to decontaminate I-beams ourselves to reduce on chemical waste
- Al bar with old switches attached to mystery tank
- option a. unscrew and completely detach from tank
- option b. cut Al bar