• Scaffolding
    • Modifications to current scaffolding around light structure this morning
  • ACE / HE
    • Green I-beams removed - finished yesterday
    • Light structure started and should be finished by latest end of day tomorrow
  • EN / EL
    •  Removed newly accessible cables inside lab as well as end caps on remaining cables below barrack by BI rack
  • SCE / HE
    • Planned date for start is week 21
  • AOB / safety
    • Fire extinguisher by HRS door
      • See photo for current vs new placement
    •  Lead
      • Finish removal this week (hopefully tomorrow)
    • Al bar with old switches attached to mystery tank has been cut
    • Balisage
      • Requested for month of May for dismantling works of RILIS in parking for IBDRS