ISOLTRAP:
- Emergency wall cutting/core drilling done and concrete evacuated (Severin/contractor). Concrete wall sides to be finalized.
- ISOLTRAP side cable tray and pipes to be lowered once the new platform floors are in place
- ISOLTRAP platform replacement work: 18th June scaffolding - first platform part to finish ~22 July.
- VITO laser tube is to stay in place: Has been discussed with the scaffolding organising responsible (Michael Bourbon). To be noted on the scaffolding contractor's work order at the next occasion.
WISARD:
- planning to come 15 - 19 June to mount the setup for off line data taking
- week 27 (29 June) to cooldown the magnet
- taking data wk27-29 until July 19
- Coordinate with ISOLTRAP & RILIS work. Crane needed for dewar craning WISARD
Beamlines:
- Vacuum rack next to the VITO setup is for vacuum equipment only and needs sorting out (Abel). See pictures AOB (Hanne)
- PUMA - RL7 installation work on supports and equipment ongoing
- PUMA LS running discussed with Richard Scrivens & Mark Kirschbaum - to secure, as planned, services from the groups from Aug '26 - start 2028.