ISOLTRAP:
- ISOLTRAP platform replacement work: 18th June scaffolding - first platform part to finish ~22 July.
- VITO laser tube is to stay in place: Has been discussed with the scaffolding organising responsible (Michael Bourbon). To be noted on the scaffolding contractor's work order at the next occasion.
WISARD:
- planning to come 15 - 19 June to mount the setup for off line data taking
- week 27 (29 June) to cooldown the magnet
- taking data wk27-29 until July 19
- Coordinate with ISOLTRAP & RILIS work. Crane needed for dewar craning WISARD
Beamlines:
- PUMA - RL7 installation work on supports and equipment ongoing
- RC6 & RL7 signal cabling (BI / Vacuum) work on the floor and mezzanine side ongoing + installation work of RL7 equipment: Severe dust and plastic parts coming down at the IDS setup + zonage not always respected / dewars being moved. Rustan has discussed it with the contractors again and we will keep a closer check.
- A few BI cables to RL7 were found to be too short are being rerouted