ISOLDE Technical Coordination Meeting (LS3)
-
-
14:00
→
14:05
General news - Review of minutes 5m
- Temporary road has been constructed and can be used for technical activities. No personnel parking in front of 508/197
Speakers: Erwin Siesling (CERN), Hanne Heylen (CERN), Joachim Vollaire (CERN) -
14:05
→
14:15
Safety matters 10m
https://home.cern/save-the-date-cern-safety-day-4-june-keeping-ourselves-and-each-other-safe/
Speakers: Hanne Heylen (CERN), James Devine (CERN), Joachim Vollaire (CERN) -
14:15
→
14:20
IBDRS, Ventilation primary areas upgrade, BTY line @ 2 GeV 5m
- Core drilling in GPS / HRS have been finalized
- Report on discussion regarding the target/line heating tests.
- Deconsignation to be initiated. Pumping/Small cooling station to be started/Local tests (Julien) half a day and BE-OP takes over. Lefteris to test computer and communication with PLC. Test planned on the 10/06. Nothing to change in controls.
Speakers: Ana-Paula Bernardes (CERN), Joachim Vollaire (CERN), Melania Averna (CERN) -
14:20
→
14:25
RILIS Laboratory upgrade project - activities update 5mSpeakers: Carlotta Porzio (CERN), Katerina Chrysalidis (CERN), Laura Lambert (CERN), Sebastian Rothe (CERN)
Week 23:
- This morning modification of scaffolding
- This afternoon starting with the removal of the shielding blocks - going for the rest of the week
- Tomorrow, carrotages dependent, we will remove the monobloc
Week 24:
- Next week modification of scaffolding holding up cables
- 2 days required for EN-EL works with RILIS, date TBC - Rustan any update?
AOB:
- BI rack to be shifted - OK?
-
14:25
→
14:35
Machine related activities in the experimental hall 10m
IS work #1.
Speakers: Erwin Siesling (CERN), Simon Mataguez (CERN)Platform EPC:
- GPS & HRS cable tests finished
- Ticket open for neaons above the platform (Jerome Cantet EN/EL)
- New beamlines depart: RY02 - RY06 'beamlines' from ERD11.06*80 (via ERK3*80) - needs final validation / connection (Nicolas David / Patrick Gallay EN/EL)
- Scaffolding will be removed wk 24 (in 2 weeks) (in parallel with construction of the scaffolding around REXTRAP)
- Platform should be ready mid-June to start commissioning
ISOLDE vacuum system:
- No change to the reporting of last week
- HRS & Replacement of the HRS20 & HRS30 pumping groups valves in the HRS separator zone (Guillermo) - Cable tests and core drilling done. Monobloc (door) to be moved Wed 03/06 after which VSC intervention can potentially be planned.
REX/HIE ISOLDE:- Digital LLRF together with replacement for REX 101MHZ Solid State amplifiers under discussion - meeting held and subject being followed up. SY/RF understands the need. More news after MTP outcome. Aiming for a conclusion before the next ISCC (18/06).
- Actions on the REX/HIE list:
- HIE: replacement prim. pumps CMs, backing & roughing lines - to be scheduled in June (VSC availability)
- Modification of the chamber of the XL9GP Quad (last in REX LINAC before CM1/DBox) (Nicolas Thaus TE/VSC). Quad to be taken out for this - to be scheduled with Antony Newborough and transport.
- Characterization of the REX RF structures in the frame of the LLRF design (Daniel Valuch, Gaimpaolo Piccinini SY/RF). No RF power, no water needed - to be scheduled (SY/RF availability)
- Removal of the obsolete 9GAP 202MHZ amplifier workaround cables (2015) from the mezzanine/MR-Tof area into the tunnel to the 9GAP structure (~11x) (Rustan Calming cable team EN/EL) - this week - REX Low E development:
- Replacement of the leaking REX mass slits actuator for a bellow type one . Discussion on remote/manual ongoing. Manual version exists and Fredrik is in favour (easier integration and installation, low costs, seldom used). - Installation in the cause of LS.
- Changes to mass slits and foils: longer stroke (100 mm) and have slightly wider slits (Fredrik). Having a (HIE ISOLDE long type) FC in this position would be beneficial (Alberto)
- Suppress the slit in the vertical part of the REX separator and instead install a 280 l/s turbo pump to increase the pumping speed in the system - in the cause of LS. - For installation of the CHROME related cables a scaffodling will be put up along the VITO and CAO line of the REXTRAP cage. Access to the door of the cage (filling) will remain. - Installation scaffolding week 24 (in 2 wks). Work will last ~2 weeks (Rustan teams)
HEBT lines Gas-distribution system commissioning:- Status
- New safety valve on its way and to be installed in the outside cage (Letizia) - check
Separator zones HRS & GPS:
- Core drilling GPS to HRS finsihed. 1 passage for survey system interconnection, 1 passage for radioactive gasses vacuum pumping line.
- GPS & HRS cable testing finished.
- GPS scaffolding to stay for later phase of core drilling (towards FE cages)?
- HRS monobloc (door to be removed wedn 03/06).
- Replacement of the HRS20 & HRS30 pumping groups valves in the HRS separator zone (Guillermo) can be planned after above actions- Attn. ventilation less operational when infrastructure/coolling water services stop (IBDRS related)?
Commissioning new target heating power supplies 170 HT room:
-
HRS & GPS target heating tests foreseen Wed 10/06:
- targets under vacuum
- water cooling for the targets running - restart Mon 08/06 (test)
- lock-out to be removed for the target heating power racks - Tues 09/06 Attn. New departs: HRS = ERD11.19*80, GPS = ERD11.4*80
- Wed 10/06: Morning tests by EPC (Julien), afternoon/parallel controls tests by OP (Lefteris) - Boris tube HRS & GPS HT tests cannot be carried out with the faraday-cages in the target zone open and machine RP protection shielding in place.
Fiber Optics work:
-
Mon 01/06 a VIC was held for hall wide installation work of the fibers (Nenad Simic EN/EL). From the 197 power room to the EPC platform, from he EPC platform to the starpoint in the old control room, from the old control room up to the GPS bunker and to the point outside the 170 REX RF room, from outside the 170 REX RF room to the Jura side of the HIE tunnel andto the MR-Tof setup (RC6). - needed to be done before scaffolding around ex-RILIS was dismounted.
-
14:35
→
14:40
Experiments related activities in the experimental hall 5mSpeakers: Hanne Heylen (CERN), Oscar Fjeld (CERN)
Ongoing
- Cleaning RL7 area for PUMA
- 2 cupboards which need to be removed before installation of ISOLTRAP platform - in contact with owners - deadline 17th of June
- WISARD and other visitors aware of G7 situation
- IDS measurement campaign
- U sample prepared by target team - awaiting feedback from RP
- Stop of water to hall from end of August:
- Possibility of mobile AC units in laser labs? On-site visit to also assess safety interlocks etc. Request from VITO at least (only 1 laser)
- Water in 508 ok, except for AC in laser labs -> does that mean ventilation in rest of the building is still working?
-
14:40
→
14:45
Experiments related activities in the experimental hall 5mSpeaker: Erwin Siesling (CERN)
ISOLTRAP:
- ISOLTRAP platform replacement work starting soon: 18th June scaffolding - first platform part to finish ~22 July.
- VITO laser tube to be kept in place (will be taken ibto account)
- Emergency exit sides and bottom smoothened with cement end of last week. Drying.
WISARD:
- planning to come 15 - 19 June to mount the setup for off line data taking
- week 27 (29 June) to cooldown the magnet
- taking data wk27-29 until July 19
- Coordinate with ISOLTRAP & RILIS work. Crane needed for dewar craning WISARD
COLLAPS/CRIS platform:
- An initial design has been made and has been transmitted to Vincent Barozier for further integration
- Position of the arrival of the laser beams onto the setup are defined: Study on an alternative for the existing (non conform) concrete structure can start
- Severin D'Armancourt and Tiago Nico (SCE) in the loop for civil engineering integration and metal structure design and calculation
VITO:
Temporary installation of a HT cage next to the REXTRAP timing rack. Little space left but only for a few months for VITO tests
Beamlines:
- RC6 MR-Tof area pre-Safety visit as organized before finalization of the HT faraday-cage, etc. (Lukas Nies, Safety inspectors)
- Cabling work in the RC6/RL7 area continuing
- PUMA floorprint indicated. Next step: exact location of the power distribution cabinet and cable trays (AC 125A x2 from RL7/PUMA appartus to B199 and Diesel)
- RL7 installation work on supports and equipment continues
- Mezzanine work on connectors finilazing.
Infrastructure / cooling and chilled water cut (IBDRS related) (dates: 19/08 - ):
- Compressed air to be kept (isolate 198/199 area from 170 area)
- 508 AC will be cut affected: Laser labs 508 will be affected
- 170 demi water 27 degrees will be cut: COLLAPS, VITO, PUMA will be affected
- 170 raw water 20 degrees will be cut: No RF power restart / LLRF characterization test with REX RF amplifiers and REX structures possible (can possibly be done without power. D. Valuch)
- (Cryo tests foreseen Q4 2027 in the frame of the integration of the LHe dewar and restart of the Cryo plant - 27 demi cooling water needed)
AOB:
- Many thanks to Anton Gunnarsson (Fredrik's student) for bringing the telescope and tripod to the COLLAPS lab in 275 yesterday 01/06
-
14:45
→
14:50
Mechanical Workshop and other support requests 5mSpeaker: Oscar Fjeld (CERN)
Last week:
- Ti44 - waiting for final measures of sample geometry
- VITO Mu-Metal bending to be done in AP
- 275 electrical workshop - cleaned
- ISOLDE logo
- Steel on building 170
- blue colour on 197
- Designs sent to Tiago to determine fastening requirements

Next week:
- Machining of holes for feedthroughs - VITO
- Cutting profiles - VITO
- Moving of soundproof cabinet from AD to ISOLDE coffee room.
-
14:50
→
14:55
Planned visits and AOBs 5m
- Next week VIP visit on Thursday afternoon
- Safety trainings affected by G7! Ad-hoc training for Wisard participants.
Speaker: Hanne Heylen (CERN)
-