ISOLTRAP:
- Work starting Thursday 18/06:
18/06: Installation de chantier
Mise en place des protections et échafaudage périphérique
Démontage des cloisons existantes au RDC
1ère phase : du 18/06 au 21/07
Démontage du plancher supérieur avec l'aide du transport
Installation de la nouvelle structure aluminium
2ème phase : du 23/07 au 18/08
Démontage du plancher inférieur
Installation de la nouvelle structure aluminium
Nettoyage et repli de chantier
- VITO laser tube to be kept in place (will be taken into account)
- Emergency exit ladder part to be installed (Severin)
WISARD:
- This week: 15 - 19 June to mount the setup for off line data taking - no cooldown= no craning limitation
- week 27 (29 June) to cooldown the magnet
- taking data wk27-29 until July 19
- Coordinate with ISOLTRAP & RILIS work.
COLLAPS/CRIS platform:
- An initial design has been made and has been transmitted to Vincent Barozier for further integration - ongoing
- Discussion on the design for mirror carying pillars ongoing: Structure or concrete (50x50cm) -> adapt platform around this
- Severin D'Armancourt and Tiago Nico (SCE) in the loop for civil engineering integration and metal structure design and calculation
IDS:
- request to remove old plastics - cannot be all removed. Easiest to close the openings with alu plates: Severin to be contacted
VITO:
- Temporary installation of a HT cage next to the REXTRAP timing rack foreseen for a few months
Beamlines:
- RC6 MR-Tof installation work continuing (Lukas / Alex)
- Cabling work in the RC6/RL7 area finsihed (few details - wk27 when cable team is back)
- Old 9 GAP RF cables going to be removed - wk27
- RL7 installation work on supports and equipment continues
- PUMA floorprint indicated.
- Visit with stakeholders for the AC distribution for the Diesel generator (199) and the PUMA AC distribution and power cabinet + AUG connection to 197.
- Easiest solution is to have the AC PUMA cabinet at the end of RL7 with drums to roll the AC cables onto when PUMA is not in place. Advantage: no permanent cable trays and cabinet in the extension zone. New design will be done by LUKAs and eventually integrated by Vincent.
- Cable work would start end of Aug wk33/34. PUMA transport not realistic before Sept anyway..
Infrastructure / cooling and chilled water cut (IBDRS related) (dates: 19/08 - May '27 ? ):
- Compressed air to be kept (isolate 198/199 area from 170 area)
- 508 AC will be cut affected: Laser labs 508 will be affected
- 170 demi water 27 degrees will be cut: COLLAPS, VITO, PUMA will be affected
- 170 raw water 20 degrees will be cut: Timeline should fit with LLRF characterization measurements of the REX RF structures (D. Valuch, G. Piccinini) & Solid State amplifier commissioning as of Sept/Oct '27 (G. Piccinini)
- Timeline should fit with Cryo tests foreseen Q4 2027 in the frame of the integration of the LHe dewar and restart of the Cryo plant - 27 demi cooling water needed (N. Guillotin, T. Dupont)