• Large shielding block removed this morning
  • Smaller shielding block to the right of HRS door likely removed sometime next week
    • to be confirmed once we finish removing services from the block
  • BI team building their new rack in the material sas as we speak, to be put in place likely this week
  • A few integration meetings this week: EN/EL and RP

 

  • Construction phase anticipated start: week 28