Primary area ventilation upgrade: - Implementation of the final routing of the HV cable for HIE ISOLDE being finalized by the beginning of next week. - Worksite will be closed.

IBDRS: - GPS dump dismantling progressing according to plan. The last to very radioactive blocks will be removed before Wed. 24/06. Remaining blocks less radioactive. - Cleaning of blocks (HAP) in building 225. - Preparing next phase for the summer, removal of black coating on the walls of Building 170. - VIC for EN-CV piping removal aling building 170 after middle of August.

 

BTY line consolidation and upgrade: